-
Continue reading →: How to perform Collapsed As-Built / As-Built But-For Schedule Delay Analysis in Primavera P6
How to perform Collapsed As-Built / As-Built But-For Schedule Delay Analysis in Primavera P6 Introduction An Collapsed As-Built / As-Built But-For Schedule Delay Analysis (ABBF) is a retrospective CPM schedule delay analysis technique that determines the earliest date that the required project completion activity, or various milestone activities could have been achieved but-for…
-
Continue reading →: Forensic / Delay Schedule Analysis – Summary Graphic Report
Forensic / Delay Schedule Analysis – Summary Graphic Report in 1 Page After performing delay analysis work in Primavera P6 or MS Project, we should make a summary graphic report for high-level manager. It would be difficult to get the overview of the analysis with a detail report like the following…
-
Continue reading →: Concurrent Delay and Pacing Delay in Construction Project
Concurrent Delay and Pacing Delay in Construction Project What is Concurrent Delay? The term “concurrent delay” is commonly used to describe circumstances where owner-caused delays and contractor-caused delays occur at the same time. In true concurrency, the owner and contractor delay events (the cause of delay) both occur at the same…
-
Continue reading →: Basic Concepts and Principles of Construction Claims
Basic Concepts and Principles of Construction Claims 1. Introduction 1.1. Construction Claims What is Construction Claims? A construction claim is the assertion of a right demanding either additional time or/and payment due to the result of an action. It is possible to meet construction claims in all construction projects. Why do…
-
Continue reading →: What is the difference between Total Float and Free Float in Primavera P6
What is the difference between Total Float and Free Float in Primavera P6 In Primavera P6, there are two important values: Total Float and Free Float. So what are the differences between them? Let’s look at the following example: There are a few tips, addressing the relationship between Total Float and…
-
Continue reading →: Typical Delay Analysis Methods in Construction Claims
Typical Delay Analysis Methods in Construction Claims This article addresses the concepts of several typical delay analysis methods in construction claims. Why do we need Delay Analysis in Construction Claims? Because The Delay Must Affect The Critical Path The Construction Contracts often state that no adjustment to the critical milestones dates or the scheduled…
-
Continue reading →: EOT Claim and Prolongation Cost Claim – The Basic Concepts
EOT Claim and Prolongation Cost Claim – The Basic Concepts Purpose of EOT It is often incorrectly thought that entitlement to an EOT automatically carries with it an entitlement to compensation for prolongation costs during the period of the EOT. The main effect of an EOT is that the Contractor is relieved…
-
Continue reading →: Concurrent Delay and Pacing Delay in Construction Claims
Concurrent Delay and Pacing Delay in Construction Claims What is Concurrent Delay in Construction Claims? Meaning of concurrent delay (from SCL Delay and Disruption Protocol 2nd Edition) True concurrent delay is the occurrence of two or more delay events at the same time, one an Employer Risk Event, the other a…
-
Continue reading →: Post 2 Test
Post 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2 TestPost 2…
-
Continue reading →: Post 01 _ Test 01
Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01 _ Test 01Post 01…
